Floors

Floor tile installation follows these steps:

  1. Surface Prep: We start by thoroughly cleaning and leveling the floor, including the potential use of a self-leveling compound based on tile and substrate.

  2. Underlayment Selection: We carefully choose the appropriate uncoupling membrane based on factors like tile size, substrate, and function to ensure a proper installation.

  3. Layout Planning: We plan the layout to maximize large tile pieces, avoid slivers, and ensure every tile's placement is known before installation.

  4. Tile Installation: Tiles are installed with polished cut edges using high-quality Ardex X5 and Ardex X77 thinset, with recommended joint widths for a clean finish.

  5. Siliconing and Grouting: We apply grout and silicone to your newly tiled shower, ensuring movement joints are siliconed to allow movement. Epoxy grout option available..